Usage
The provided steps also apply to Add-on Upgrade Plans.
1
Navigate to an In-Progress Plan
- In the left-hand column of the Chkk Dashboard, expand Upgrade Copilot.
- Click Upgrade Plans, then select Clusters.
- Identify the Upgrade Plan currently in In Progress status that you want to complete.
2
Open the Completion Modal
- Next to the plan entry, click the checkmark icon.
- A confirmation modal will appear once you click it.
3
Confirm Completion
- (Optional) Add any comments you wish to include about the plan’s outcome.
- Click Mark as Complete to finalize the completion process.
4
Verify Completion Status
- Once marked complete, the Upgrade Plan becomes read-only and appears with a Completed status.
- The Marked Completed by column updates to show the name of the user who completed the plan.